Project Tracking

Jones Home


  • Address: 1234 Josephine
  • Model: Alpine
  • Start Date: November 15, 2016
  • End Date: February 26, 2016
jQuery UI Progressbar - Default functionality
 

Construction Process

 
drop-1.png

Status: 

Notes:

Getting Started – 4-6 Weeks

By: Silas Coleman

Start Date: November 15, 2016

Completion Date: December 15, 2016

Time: 30 days

  • Contract with all structural options
  • Choose design selections
  • Purchase orders issued
  • Clear and/or rough grading of homesite
  • Buyer conference / Pre-construction meeting
jQuery UI Progressbar - Default functionality
 

 
 
foundation.jpeg

A Solid Foundation – 1-2 Weeks

By: Silas Coleman

Start Date: November 15, 2016

Completion Date: December 15, 2016

Time: 30 days

  • Excavate, set forms, install rebar and pour foundation
  • Pour garage floor
 

 
 
framing.jpeg

Framework – 2-3 Weeks

By: Silas Coleman

Start Date: December 20, 2016

Completion Date:  Estimated @ January 15, 2016

Time: TBD

 

 
drop-1.png
 

 
 

Mechanical  2-3 Weeks

By: Peterson Electric, phone # 970-466-4732

Start Date: November 15, 2016

Completion Date: December 15, 2016

Time: 30 days

  • Rough mechanicals: heating, AC, plumbing and electrical
  • Install exterior siding and trim

Rough Electric

By: Smith & Jones Mechanical

phone # 970-466-4732

Start Date:

January 3, 2017

Completion Date:

Est January 10,  2016

Time: TBD

Rough Mechanical

By: Smith & Jones Mechanical phone

970-466-4732

Start Date: 

January 3, 2017

Completion Date: 

Est January 10,  2016

Time: TBD

Rough Plumbing

By: Copper John Plumbing

phone # 970-466-4732

Start Date: 

January 3, 2017

Completion Date: 

Est January 10,  2016

Time: TBD

wrench.png
 

 
 
cabinets.jpeg

Interior Details – 3-4 Weeks

By: Silas Coleman

Start Date: November 15, 2016

Completion Date: December 15, 2016

Time: 30 days

  • Insulation and sealant package completed
  • Drywall installed
  • Flooring installed
  • Cabinets and countertops installed
  • Interior trim and doors installed
  • Exterior and interior painting completed

Finish Electric

By: Smith & Jones Mechanical

phone # 970-466-4732

Start Date:

January 3, 2017

Completion Date:

Est January 10,  2016

Time: TBD


Insulation

By: I.M. Warm Insulation Co.

phone # 970-466-4732

Start Date:

January 3, 2017

Completion Date:

Est January 10,  2016

Time: TBD

Finish Mechanical & HVAC

By: Smith & Jones Mechanical

phone # 970-466-4732

Start Date:

January 3, 2017

Completion Date:

Est January 10,  2016

Time: TBD


Cabinets

By: Custom Cabinets

phone # 970-466-4732

Start Date:

January 3, 2017

Completion Date:

Est January 10,  2016

Time: TBD

 

 
 
carpet.jpeg

Installation – 3-4 Weeks

By: Silas Coleman

Start Date: November 15, 2016

Completion Date: December 15, 2016

Time: 30 days

  • Final Mechanical installed: HVAC, plumbing and electric
  • All fixtures installed
  • Appliances installed
  • Carpet, tile and wood floors installed

Flooring

Have Knees Flooring

phone # 970-466-4732

Start Date:

January 3, 2017

Completion Date:

Est January 10,  2016

Time: TBD

 

 

 

Appliances

Acme Appliance

phone # 970-466-4732

Start Date:

January 3, 2017

Completion Date:

Est January 10,  2016

Time: TBD

 

 
 
walk thru.jpeg

Finishing Touches – 2-3 Weeks

By: Silas Coleman

Start Date: November 15, 2016

Completion Date: December 15, 2016

Time: 30 days

  • Final punch list
  • House thoroughly cleaned
  • Walk through orientation (approx. 1 week prior to closing)
  • Final walk through
  • Closing on the house
home.png
 
 

Notes: